A named sponsor with decision authority
One accountable individual who can confirm the decision question, resolve access blockages and receive escalation. Without this the phase stalls in week two.
Mandate opening
The opening phase exists to establish what is actually being decided, who may decide it, what evidence exists, and what stands in the way of a defensible answer. It is bounded and it ends with a decision point, including the decision not to continue.
The phase
Duration
Approximately thirty days from mobilisation. Where a decision deadline is shorter, the phase is compressed and the compression is recorded as a limitation on the record it produces.
Days 1–5
The decision is written down as a single answerable question, with the alternatives it is being chosen between. Decision rights, the sponsor, the approving body and the point of no return are confirmed in writing. Ambiguity here is the most common cause of unusable work later.
Produces
Decision statement and authority map, confirmed by the sponsor.
Days 1–12
Everything the organisation already holds is taken in and registered with its source, date and interest. Nothing is accepted as background. An information request list identifies what is missing and who must supply it.
Produces
Evidence register with provenance and an outstanding-information list.
Days 6–20
Conflicts between sources are surfaced and classified rather than smoothed over: resolved on evidence, resolved as definitional, unresolved and material, unresolved and immaterial, or escalated.
Produces
Contradiction register with a disposition against each entry.
Days 8–22
The parties whose consent, capability or inaction determines the outcome are identified, along with the institutional, operational, regulatory and payment constraints the plan depends on but has not tested.
Produces
Stakeholder and dependency map with the constraints each imposes.
Days 18–28
The basis is assembled: what is established, what is corroborated, what is indicative, what is contested and what remains unknown, with the reasoning that connects evidence to a position.
Produces
Initial decision record with graded findings and stated assumptions.
Days 22–30
A separate, deliberately unflattering document setting out what could not be established, what would change the answer, and what the organisation would be accepting if it proceeded anyway.
Produces
Unresolved-risk memorandum, written to survive later scrutiny.
Day 30
A working session with the sponsor and decision-makers. Three outcomes are legitimate: proceed to decision on the basis established, continue examination against a defined gap, or stop. Stopping is a valid conclusion and is recorded as one.
Produces
Checkpoint record with the agreed disposition and any decision conditions.
These requirements are stated before engagement because a mandate that cannot obtain them produces a weaker record, and the record says so.
One accountable individual who can confirm the decision question, resolve access blockages and receive escalation. Without this the phase stalls in week two.
Papers, models, board material, correspondence, agreements and prior advice — including the parts that are unflattering or superseded. Withheld material becomes an unresolved risk in the memorandum.
Typically four to eight attributable conversations across commercial, operational, finance and legal functions. These are recorded as attributed representations, not anonymous colour.
Definition at the outset, a mid-phase contradiction review, and the day-30 checkpoint. Each is a working session, not a presentation.
Counterparty, regulator or third-party enquiry is agreed in advance, including whether the mandate is disclosed. Sensitivity constraints are recorded, and their effect on what can be verified is stated.
The accountable principal conducts the examination and signs the record. The phase is not staffed to a junior tier and reviewed at the end.
Output is a governed record with provenance intact, not a slide deck. Sessions discuss the record; they do not replace it.
Conflict and independence checks are completed before the phase starts, and any position that would compromise the work is disclosed or the mandate is declined.
Scope, duration, deliverables and fees are agreed in the engagement terms before work begins. They are mandate-specific and are not published as packages or list prices.
On commercial terms
Boundaries
The format of the record this phase produces is illustrated by the synthetic specimen decision record, and the standard governing how its findings are graded is the Evidence Standard.
Next decision
An opening conversation establishes the decision in question, the access available and whether this phase is the right instrument for it.